 |
Ask the Superintendent - September
26, 2007
On Wednesday, September 19th, as the invited
guest speaker at the Goshen Chamber of Commerce’s
monthly breakfast, I was asked to address how the
growth in Goshen community is impacting our schools.
I would like to highlight some of the points I made
that morning.
Before any school district enters into a building
project there are a number of key
factors that must be addressed and carefully
studied:
- Need –
Currently three of our four schools (GHS, CJH,
SAS) are functioning beyond the student rated
capacity. Only the Goshen Intermediate School is
at the rated capacity. A school district must
have space to meet the challenges of an
increasing student enrollment. In addition to
physical space, equally important is the ability
to maintain and improve academic programs. We
have recently commissioned professional
demographic studies in our attempt to forecast
the future enrollment trends in our district.
The first study, in January of 2006, indicated
our student enrollment is going to continue to
grow. The second study completed on August 13,
2007, reinforced that our student enrollment was
increasing at a slightly faster rate (2%) than
the previous study in January of 2006. Even if
new construction slows, our district is still
going to experience some increase in enrollment
from this sector, plus additional students from
the sale of existing homes in our community.
- Cost – It is
essential that school districts carefully
scrutinize the cost of any building project. The
key concept in this process is the creation of
needed space for enrollment and program and
still build at the lowest possible cost. It is
important to work in concert with the architect
and the construction management firm to obtain
the lowest possible contractor bids and to apply
state aid ratios effectively to maximize our
construction aid. Critically important in this
process is to insure our building aid units
reach their highest potential.
- Timetable –
Anytime a school district enters into a building
program, whether it be building a new school or
additions to existing structures it is an
exceptionally complicated and lengthy process.
By way of example, if we were to start a
building project today, (September of 2007) the
newly constructed or renovated schools would not
be completed or ready to receive students at the
earliest until September of 2012. The drawing
and design process in addition to the actual
construction requires a five-year time span. If
you add the 2½ years of meetings, research, and
planning that has been completed by the Growth
Task Force, we end up with a 7½ year process.
- The
Consequence of Not Building - There is a cost to
waiting. Since construction costs are increasing
on an average of 8% to 9% per year, if we wait
to build it will cost more and we will receive
less. If we do not expand our facilities to meet
the coming challenges, student enrollment is
still going to increase.
- Community
Involvement in Planning – For the last 2½ years
a representative group of approximately 30
community members have met monthly to plan for
the future needs of our school district. This
committee has studied and reviewed all the
complex issues related to enrollment growth and
the impact it will have on our district.
In a future article
I will explain the role the Growth Task Force has
played in this process.
Roy Reese
Superintendent of Schools
|
 |